Tyra West Upper Pipe Bridge

The Upper Pipe Bridge links the IPF module and the Tyra West Bridge Module of the Tyra West Platform complex. The bridge is part of a major extension of the existing production facilities including the installation of new gas processing facilities and a bridge module.

  • LocationTyra West block 5504/11-12
  • DimensionsLength 98 metres Width 6 metres Height 7 metres
  • Weight260 tonnes
  • Contract AwardJune 1995
  • CompletionJanuary 1996
  • ContractPC
  • ClientMaersk Olie og Gas