K1A Jacket

Jacket with 4 skirt piles. The buoyancy of the jacket was used for turning over the jacket during offshore installation. Due to the soft soil condition, 4 underleg piles, installed with a template, were used in order to achieve stability during pile driving. The connection between sleeves and piles was grouted.

  • LocationK1A
  • Dimensions25x25x65 metres
  • WeightJacket 940 tonnes
    Piles 740 tonnes
  • Contract AwardJune 2000
  • CompletionJune 2001
  • ContractEPC Client Total
  • Subcontract fromSHL

Back to overview